PMP Guide — Empowering Project Managers
ProcessPredictiveHardECO: Process Task 5.1

PMP Practice Question: Process — Predictive, Hard

You are managing a software implementation project for a financial services client using a predictive approach with a detailed WBS and network diagram. During the planning phase, you identified a critical dependency: the data migration activity (Activity M, 15 days duration) cannot start until both the database configuration (Activity D, 10 days) and the data cleansing validation (Activity V, 12 days) are complete. Activities D and V can occur in parallel and both start after user requirements approval (Activity R, 8 days). Activity M is followed by user acceptance testing (Activity T, 20 days). If Activity R starts on Day 1, what is the earliest day that user acceptance testing can be completed, and what type of dependency exists between Activities D and V relative to Activity M?

← All questions

Study this topic