PMP Practice Question: Business Environment — Hybrid, Hard

A manufacturing company is running a hybrid Industry 4.0 project implementing IoT sensors (agile sprints) and an ERP upgrade (predictive phases). The project is structured with separate agile and predictive teams reporting through a unified PMO. In Month 7, a private equity firm announces acquisition of the company, expected to close in 90 days. The acquiring firm's CIO indicates they will evaluate all technology initiatives post-acquisition and mentions their portfolio uses a different ERP platform. The IoT sensor deployment is 60% complete and delivering measurable efficiency gains, while the ERP upgrade has completed design and is entering the build phase. The project budget is $4.2M with $2.1M spent. How should the project manager navigate this organizational change?