An agile team of eight members has been working together for three months. The Product Owner notices that two developers, who are both highly skilled but have different technical philosophies, frequently disagree during daily standups and refinement sessions. These disagreements sometimes delay decisions and create tension. Other team members have started avoiding technical discussions when both developers are present. Yesterday, a refinement session ended early because the disagreement escalated into a heated argument. What is the most appropriate action for addressing this conflict?