PMP Guide — Empowering Project Managers
ProcessHybridMediumECO: Process Task 2.1

PMP Practice Question: Process — Hybrid, Medium

You are managing a hybrid project where the product development team works in two-week sprints while the regulatory compliance team follows a waterfall approach with predefined milestones. During sprint planning, the development team commits to features that require compliance documentation, but the compliance team indicates they need four weeks' advance notice to complete their reviews. This misalignment has caused delays in three consecutive sprints. What should you do to address this integration challenge?

← All questions

Study this topic