PMP Guide — Empowering Project Managers
ProcessPredictiveEasyECO: Process Task 3.1

PMP Practice Question: Process — Predictive, Easy

You are managing a construction project to build a new office building. During the planning phase, you identify that specialized steel beams must be ordered from an overseas supplier with a 12-week lead time. The beams are needed in week 20 of the project schedule. Your team is currently in week 2 of the project. What should you do first?

← All questions

Study this topic

PMP Practice Question — Process · Easy | PMP Guide