PMP Practice Question: Process — Predictive, Medium
During the execution phase of a manufacturing facility upgrade project, a key supplier informs you that a critical component will be delayed by three weeks due to supply chain disruptions. This component is on the critical path and is needed for installation activities scheduled to begin in four weeks. You have a contingency reserve allocated in the budget, and the schedule baseline includes buffer time but not specifically for this activity. The delay will impact subsequent critical path activities. What is the BEST course of action?
Study this topic
- 📖Issue and Risk Logs: Complete Guide for Project Managers
Master issue and risk log management with proven techniques aligned with PMBOK 8th Edition. Learn how to track, prioritize, and resolve project challenges effectively.
- 📖Schedule Management Techniques for Modern Project Teams
Master critical path, critical chain, agile scheduling, and hybrid approaches for the 2026 PMP exam. Learn practical techniques that align with PMBOK 8th Edition principles.
- 🗂️Flashcards: Risk Responses, Reserves & Contract Types
14 cards · quick recall practice
More Process Questions
View all →You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. During month 6, you conduct an earned value analysis and discover that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks you to forecast the final project cost and determine what actions are needed. Using the current performance trends, what is the most appropriate estimate at completion (EAC) if you believe current variances are atypical and future work will be performed at the planned rate?
You are leading a software development project using a predictive approach. The project sponsor has approved the project charter, and you are now ready to begin detailed planning. Your next step is to gather requirements from stakeholders to understand what the software must accomplish. Which process group are you currently working in?
You are managing a bridge construction project and have just completed developing the Work Breakdown Structure (WBS) with your team. Each work package has been defined and assigned a unique identifier. A team member asks what the lowest level of the WBS represents. How should you respond?
