PeopleHybridHardECO: People Task 1.1

You are managing a hybrid project where the core development team uses Scrum while regulatory compliance activities follow a predictive approach. During a retrospective, several developers express frustration that the compliance team repeatedly requests detailed documentation mid-sprint, disrupting their flow. The compliance lead argues these requests are non-negotiable due to audit requirements. Team morale is declining, and velocity has dropped 25% over the last two sprints. What should you do first to address this conflict?