ProcessPredictiveMediumECO: Process Task 11.2

Your manufacturing equipment upgrade project is in the executing phase. A key vendor has submitted deliverables for the third milestone, but during the inspection process, your quality assurance team identifies that 15% of the components do not meet the specifications outlined in the procurement contract. The vendor claims the specifications were ambiguous and requests additional payment to remake the components. This is causing a potential two-week delay. What is the BEST course of action?