Your construction project uses a hybrid approach where procurement and permitting follow predictive methods, while interior design selections use an iterative approach with the client. The general contractor has reported that the foundation work (on the predictive critical path) is 15% behind schedule due to weather delays. Meanwhile, the client wants to accelerate the interior design iterations to make faster decisions. The project has a fixed completion date for regulatory reasons. What should be your primary focus?