PMP Practice Question: PeoplePredictive, Medium

You are managing a software implementation project using a waterfall methodology for a financial services client. During the design phase, you discover that one of your key business analysts, who is responsible for defining critical system requirements, lacks experience with the specific regulatory compliance requirements of the financial industry. This knowledge gap was not apparent during resource assignment. The design phase is scheduled to complete in six weeks, and this analyst is already assigned full-time to your project. What should you do?

← All questions
📖

Study this topic

PMI-ACP After PMP: Your 2026 Certification Pathway

Already have your PMP? Learn how to leverage your certification toward PMI-ACP, including prerequisites, exam structure,

More People Questions

View all →
1
MediumAgile

During sprint planning, your development team commits to 45 story points based on historical velocity. However, your product owner insists they must complete 60 story points this sprint because of a commitment made to a key stakeholder. The product owner argues that the team 'just needs to work harder' and threatens to escalate to senior management if the team doesn't comply. The team looks to you, the Scrum Master, for guidance. How should you respond?

2
MediumAgile

Your agile team has a new member, Sarah, who joined two weeks ago. Sarah has strong technical skills but comes from a traditional waterfall background. During the current sprint, you notice Sarah working in isolation, not updating the task board, and not asking for help despite her story being blocked. In the standup, she reports 'everything is fine' even though you can see she's struggling. Other team members have offered help, but she politely declines. What is the most effective way to help Sarah adapt to the agile team environment?

3
MediumAgile

Your agile team has been consistently meeting sprint commitments, but during a recent retrospective, team members admitted they have been padding estimates significantly to ensure they never miss a commitment. The team's capacity allows them to complete stories early, but they wait until late in the sprint to pull in additional work to avoid looking like they overcommitted. The product owner is frustrated because the team could be delivering more value. What should you do to address this behavior?