PMP Guide — Empowering Project Managers
Business EnvironmentPredictiveMediumECO: Business Environment Task 1.2

PMP Practice Question: Business Environment — Predictive, Medium

A construction project manager is executing a municipal building project with a $5 million budget funded by a government bond. Midway through the project, economic conditions change and interest rates increase significantly, causing the municipality's borrowing costs to rise by 40%. The finance department informs the project manager that no additional funding will be available beyond the original budget. The project is currently 45% complete and has spent 42% of the budget, with performance tracking showing a CPI of 1.07 and SPI of 1.03. How should the project manager respond to this budget constraint?

← All questions

Study this topic