PMP Practice Question: Process — Hybrid, Medium

A project manager is leading a hybrid project to implement a new customer relationship management (CRM) system. The infrastructure and data migration components are being delivered using a predictive approach with fixed milestones, while the user interface customization is being developed iteratively using Scrum. During sprint planning, the development team identifies dependencies on the data migration work, which is running two weeks behind schedule. The team is concerned they won't be able to complete their committed sprint work without the migrated data. What should the project manager do first?