PMP Practice Question: Business Environment — Hybrid, Hard

Your organization is implementing a new regulatory compliance system using a hybrid approach. The predictive portion involves hardware infrastructure deployment (6 months), while the adaptive portion covers software feature development in 2-week sprints. During sprint planning, the compliance team identifies that new financial regulations will be published in 3 months, requiring significant software changes. However, the hardware deployment schedule cannot be accelerated due to vendor constraints and facility requirements. The executive sponsor is concerned about achieving compliance by the regulatory deadline. What should you do first?