PMP Practice Question: Business Environment — Hybrid, Medium

You are leading a hybrid project to implement an enterprise resource planning (ERP) system. The data migration and system configuration follow a waterfall methodology, while process optimization workshops and training are conducted in iterative cycles. Six months into the 18-month project, your organization's board of directors approves a merger with a European competitor. The merged entity will have different reporting requirements, multiple currencies, and additional regulatory compliance needs. Your sponsor asks you to assess the project's viability. What should be your primary consideration?