PMP Practice Question: ProcessPredictive, Medium

You are managing a construction project using a predictive approach. During the execution phase, a major supplier informs you that a critical material will be delayed by three weeks due to manufacturing issues. The project schedule shows this material is on the critical path, and the delay will impact the project completion date. You review the risk register and find this supplier delay was identified as a potential risk with a mitigation strategy documented. What should you do first?