ProcessPredictiveEasyECO: Process Task 1.2

Your team is developing a project schedule for a manufacturing facility upgrade. You have identified all activities, sequenced them, and estimated their durations. Several team members have been assigned to multiple concurrent activities. What should you do next to complete the schedule development process?