PMP Guide — Empowering Project Managers

Practice Questions

PMP Practice Questions

Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.

25 questions found

1
PeoplePredictiveHard

You are managing a defense contractor project with 30 team members working on classified deliverables. Three months into the project, a key architect who designed the overall solution structure has received a more lucrative offer from a competitor and will leave in two weeks. This architect's knowledge is essential for the next phase, and direct replacement is complicated by security clearance requirements that take 4-6 months. You have identified an internal candidate with relevant experience but who lacks the specific domain expertise. The project baseline includes detailed technical specifications, but much of the architect's design rationale exists only in email threads and meeting notes. Your sponsor is pressing you to maintain the current schedule. What is your best course of action?

August 20, 2026

2
PeoplePredictiveHard

You are managing a large construction project that has entered the execution phase. During a routine performance review, you discover that one of your site supervisors has been consistently inflating progress reports for the past three weeks, showing 85% completion when actual completion is closer to 65%. This supervisor is well-liked by the team, has 15 years of experience, and this is the first time you've encountered integrity issues with this individual. The misinformation has affected your earned value calculations and led you to reassign resources that were actually still needed. The project is visible to executive leadership, and you have a steering committee meeting in two days. What is the most appropriate course of action?

August 20, 2026

3
PeoplePredictiveHard

You are leading a pharmaceutical project to develop validation documentation for a new manufacturing process. The project team includes quality assurance specialists, process engineers, and regulatory affairs experts. During a critical review meeting, you observe that the QA specialists consistently dismiss input from the process engineers, citing regulatory concerns, while the engineers feel the QA team doesn't understand operational realities. This dynamic has resulted in rework cycles and is threatening the project's ability to meet regulatory submission deadlines. The organizational matrix structure gives you limited authority over these functional resources. How should you address this situation?

August 20, 2026

4
PeoplePredictiveHard

You are managing a government contract project following a predictive approach with strict scope, schedule, and budget constraints. During month 4 of the 12-month project, a key team member who holds critical institutional knowledge about legacy systems unexpectedly resigns. This team member was responsible for integrating the new system with three legacy platforms, and replacement hiring could take 6-8 weeks due to security clearance requirements. The integration work is scheduled to begin in 3 weeks. Your team suggests aggressively cross-training other members, but this would require pulling resources from their current critical path activities. What should you prioritize first?

August 20, 2026

5
PeoplePredictiveHard

You are managing a complex infrastructure project with a team of 45 members across three geographical locations. During the executing phase, you notice that two senior technical leads from different locations are consistently disagreeing on technical approaches during virtual meetings, causing delays in decision-making. The disagreements have begun to affect team morale, and other team members are starting to take sides. Both leads are highly skilled and their expertise is critical to project success. The project is currently on schedule but at risk of delays if this conflict continues. What is the most appropriate action to take?

August 20, 2026

6
PeoplePredictiveHard

Your pharmaceutical project team of 30 specialists is executing a predictive plan to develop regulatory submission documentation. You have one team member, a senior regulatory expert with 20 years of experience, who possesses unique knowledge critical to project success but consistently demonstrates poor mentoring skills, dismisses junior team members' questions as 'basic,' and has caused two junior regulatory writers to request transfers. The junior members are necessary for document production volume, but the senior expert's specialized knowledge of FDA interactions cannot be easily replaced. Your HR business partner has documented complaints but states the expert has not violated any policies. The project is at the midpoint and approaching critical regulatory milestones. What is your best approach?

July 27, 2026

7
PeoplePredictiveHard

You are leading a construction project that is 60% complete. During a routine team performance assessment, you discover that your site supervisor has been consistently inflating progress reports to make their team appear more productive. Upon investigation, you learn the supervisor was responding to intense pressure from the construction manager to meet aggressive milestones, and feared their team would be viewed negatively. The actual progress indicates the project is approximately 3 weeks behind schedule. The construction manager is unaware of the misreported data and is making decisions based on the inflated reports. What should you do?

July 27, 2026

8
PeoplePredictiveHard

You are managing a government defense project with strict security clearance requirements and a hierarchical organizational structure. A high-performing team member has been consistently delivering excellent technical work but has begun circumventing the established approval chain by directly contacting the client's technical lead to expedite decisions. While this has accelerated some approvals, your project sponsor has received a formal complaint from the client's program manager about protocol violations. The team member argues their actions have saved the project two weeks of schedule delays. How should you address this situation?

July 27, 2026

9
PeoplePredictiveHard

Your predictive project is entering month 8 of a 14-month schedule. Three team members who were critical resources for the design phase have been reassigned to other organizational priorities by their functional managers, despite your resource management plan identifying them as needed through month 10. The remaining team has the technical skills but lacks the institutional knowledge these members possessed. The project sponsor is pressuring you to maintain the original schedule. Performance reviews show current team morale is declining. What is your best course of action?

July 27, 2026

10
PeoplePredictiveHard

You are managing a large infrastructure project with a team of 45 members across engineering, procurement, and construction disciplines. During the execution phase, you notice that two senior engineers who must collaborate on critical path activities have fundamentally different working styles—one prefers detailed documentation and formal approvals, while the other favors quick decisions and minimal paperwork. Their conflict is causing delays in design reviews that are impacting the project schedule. The procurement lead suggests reassigning one engineer to a different work package. What should you do first?

July 27, 2026

11
PeoplePredictiveHard

You are managing a critical infrastructure project for a utility company with a 36-month timeline and a highly structured governance framework. Six months into execution, your most senior electrical engineer, who serves as a technical authority and mentors three junior engineers, begins showing signs of stress and reduced engagement. Their deliverable quality remains acceptable, but they are increasingly absent from team meetings, less responsive to questions, and have stopped participating in design reviews. Two junior engineers have privately expressed concern. When you meet with the engineer, they acknowledge feeling overwhelmed but are reluctant to discuss specifics, saying 'it's personal' and they'll work it out. Your next major design milestone requiring their expertise is in five weeks. The project has no schedule buffer. What is the MOST appropriate course of action?

July 13, 2026

12
PeoplePredictiveHard

You are managing a complex manufacturing facility upgrade project for an automotive supplier. The project has a fixed-price contract with milestone-based payments. Your project team includes 12 full-time employees and 18 contractors from three different vendors. At the 60% complete point, you learn that two contractors from Vendor A have been socializing with your client's procurement director outside of work and have mentioned they could deliver certain components 'more efficiently' if contracted directly by the client, bypassing your organization. Your contracts manager confirms this would violate the exclusivity clause in your vendor agreement. The contractors are performing well technically, and replacing them now would delay the project by 4-6 weeks, risking a $200,000 milestone payment. What should you do?

July 13, 2026

13
PeoplePredictiveHard

You are managing a defense contract project with 35 team members across four locations. The contract includes specific earned value management (EVM) reporting requirements. At the month 9 performance review, you notice that one remote team of eight developers consistently reports 100% completion of planned tasks on time, yet integration testing repeatedly uncovers significant defects requiring rework. The team lead is well-liked and has been with the company for 15 years. Other teams have expressed frustration about the rework burden. Your SPI is 1.02 but CPI is 0.87, partly due to these rework costs. When you discuss this with the team lead privately, they explain their team is working hard and meeting their commitments as they understand them. What is the MOST effective way to address this performance issue?

July 13, 2026

14
PeoplePredictiveHard

You are leading a pharmaceutical product development project following a waterfall approach. During the detailed design phase, your quality assurance lead raises concerns that the technical lead is making design decisions without consulting the regulatory compliance specialist, potentially creating future audit risks. When you investigate, you discover the technical lead believes the compliance specialist is being overly cautious and slowing down progress. The technical lead has 20 years of experience and has successfully delivered similar projects. The compliance specialist is newer to the company but has deep regulatory expertise. Your project has strict regulatory submission deadlines with significant financial penalties for delays. How should you address this situation?

July 13, 2026

15
PeoplePredictiveHard

You are managing a large government infrastructure project with a baseline budget of $45 million and a 24-month timeline. At month 16, a critical team member who holds specialized knowledge about legacy system integration submits their resignation, citing personal reasons. This team member has been instrumental in interfacing with three key stakeholders and possesses undocumented institutional knowledge. The project is currently on schedule but slightly over budget (CPI 0.92). Your sponsor is concerned about the impact on the upcoming integration phase scheduled to begin in three weeks. What should be your FIRST action to address this situation?

July 13, 2026

16
PeoplePredictiveHard

You are managing a complex infrastructure project using earned value management and a predictive approach. Your project has a CPI of 0.92 and SPI of 0.88, indicating both cost and schedule challenges. During a difficult steering committee meeting, your sponsor publicly criticizes your leadership and questions your competence in front of other executives and your project team members who were presenting. The sponsor demands immediate corrective actions and threatens to replace you if performance doesn't improve by next month. After the meeting, your team members express concern about the public criticism, and you sense their confidence in the project's success is wavering. What should be your FIRST priority in responding to this situation?

July 10, 2026

17
PeoplePredictiveHard

You are managing a multinational aerospace engineering project with team members across five countries and three time zones, following a stage-gate predictive methodology. During the design phase, you discover that your lead engineers in Germany and Japan have been making conflicting technical decisions in their respective subsystems, each believing they had authority over the integration approach. This has resulted in incompatible design specifications that were just revealed during a scheduled integration review, three weeks before the gate review. Both engineers are highly respected technical authorities who report to different functional managers in a strong matrix organization. The functional managers are now involved and supporting their respective engineers' approaches. How should you address this situation?

July 10, 2026

18
PeoplePredictiveHard

You are managing a pharmaceutical manufacturing facility construction project following a waterfall approach. During the executing phase, you notice that your quality manager and construction manager have fundamentally different interpretations of the acceptance criteria in the approved requirements specification. The quality manager insists on FDA pharmaceutical-grade standards for all areas, while the construction manager argues that only clean room areas require this level, with administrative areas following commercial building standards. Both cite different sections of the 300-page requirements document. This disagreement is causing daily conflicts, delaying inspections, and creating team tension. How should you resolve this conflict?

July 10, 2026

19
PeoplePredictiveHard

You are leading a government IT system integration project using a predictive lifecycle with a dedicated team of 25 members. Six months into the 24-month project, organizational metrics show your team's velocity is 15% below the planned baseline, though quality metrics remain acceptable. During a retrospective session, team members confidentially share that the project's strict command-and-control governance structure, mandatory daily status emails, and your directive leadership style are demotivating them. Several high performers hint they are exploring other opportunities. However, the government client has explicitly required this governance approach due to previous project failures, and your sponsor strongly supports maintaining tight controls. What is the BEST course of action?

July 10, 2026

20
PeoplePredictiveHard

You are managing a critical defense infrastructure project with a fixed 18-month timeline and strict requirements documentation. Three months into execution, your technical lead, who designed the entire system architecture, submits a resignation effective in two weeks to join a competitor. This person holds critical knowledge not fully documented, and the remaining team members have varying levels of expertise. Senior management is extremely concerned about project continuity and wants to prevent knowledge loss. What should be your FIRST action as project manager?

July 10, 2026

21
PeoplePredictiveHard

You are managing a complex aerospace engineering project with a 36-month timeline using earned value management (EVM) for performance tracking. Your project has a CPI of 0.89 and SPI of 0.92 at the 12-month mark. The executive steering committee is considering canceling the project due to poor performance. Your analysis reveals that performance issues are concentrated in one engineering team led by a manager who has been with the company for 18 years and has strong relationships with senior executives. This manager is resistant to your process improvement suggestions and has stated that 'engineering excellence cannot be rushed.' Other team leads have privately expressed frustration with this manager's team missing dependencies. The manager's functional director is defensive of their employee and suggests the schedule was unrealistic from the start. What should be your PRIMARY focus to address this situation?

June 1, 2026

22
PeoplePredictiveHard

You are managing a multinational IT implementation project with team members across five countries spanning four time zones. The project follows a traditional waterfall approach with phase gates. Your project management office (PMO) requires weekly status meetings with all core team members present. After three months, you notice declining participation, with team members frequently joining late, multitasking during meetings, or sending delegates. Survey feedback reveals that team members find the meetings unproductive and poorly timed for their time zones. However, the PMO director insists the meeting format is a governance requirement and cannot be changed. Your sponsor is concerned about team engagement scores dropping from 85% to 62%. What is the BEST way to address this situation?

June 1, 2026

23
PeoplePredictiveHard

You are managing a government construction project with a fixed-price contract and a defined scope. Six months into the 18-month project, a new government regulation is enacted that requires additional safety measures, impacting 30% of the completed work and all remaining work. Your project team is demoralized because they believe they will need to redo work that was compliant at the time of completion. The compliance officer insists all work must meet the new standards before final acceptance. The sponsor indicates no additional budget is available and expects you to absorb the changes. During a team meeting, several senior team members openly criticize the sponsor's position and question the project's viability. How should you address this situation?

June 1, 2026

24
PeoplePredictiveHard

You are leading a pharmaceutical product development project following a waterfall methodology with strict regulatory requirements. Your quality manager reports that three team members from the testing department have been consistently missing defect documentation deadlines, causing delays in the validation phase. Upon investigation, you discover these team members are also assigned to two other critical projects and are working 60-70 hours per week. The functional manager states they cannot provide additional resources due to budget constraints. The testing phase must be completed in four weeks to meet the regulatory submission deadline. What is the MOST effective approach to address this situation?

June 1, 2026

25
PeoplePredictiveHard

You are managing a large infrastructure project with a 24-month timeline using a predictive approach. During the execution phase, your technical lead, who has been with the project since initiation and possesses critical knowledge about legacy system integrations, submits their resignation with a two-week notice. The project is currently 40% complete, and the integration work is scheduled to begin in six weeks. Your sponsor is concerned about the impact on the project schedule and is pressuring you to immediately hire a replacement at a higher salary to retain institutional knowledge. What should be your FIRST action as the project manager?

June 1, 2026