PMP Practice Question: Process — Hybrid, Hard

You're managing a hybrid project to modernize a legacy system. Phase 1 (months 1-4) uses predictive approach for infrastructure and data architecture, while Phase 2 (months 5-10) uses Scrum for application development. You're now in month 3, and the infrastructure team has encountered unexpected complexity that will delay their completion by 6 weeks, pushing into month 5.5. The development team's sprint 0 is scheduled for month 5, and team members are already assigned. Waiting would idle 8 developers for 6 weeks at $180K cost. The development team suggests they could begin working on independent modules using simulated infrastructure. What factors should most heavily influence your decision?