PMP Practice Question: Process — Hybrid, Hard
You're managing a hybrid project to modernize a legacy system. Phase 1 (months 1-4) uses predictive approach for infrastructure and data architecture, while Phase 2 (months 5-10) uses Scrum for application development. You're now in month 3, and the infrastructure team has encountered unexpected complexity that will delay their completion by 6 weeks, pushing into month 5.5. The development team's sprint 0 is scheduled for month 5, and team members are already assigned. Waiting would idle 8 developers for 6 weeks at $180K cost. The development team suggests they could begin working on independent modules using simulated infrastructure. What factors should most heavily influence your decision?
Study this topic
- 📖Cost Estimation Techniques: From ROM to Definitive Estimates
Master the cost estimation methods tested on the PMP exam, from rough order of magnitude to definitive estimates, with practical examples and calculation techniques.
- 📖AI in Project Management: Your 2026 PMP Exam Guide
Master AI concepts for the 2026 PMP exam. Learn how artificial intelligence impacts project management, what you need to know for test day, and practical applications.
- 🗂️Flashcards: Earned Value Management (EVM) Formulas
16 cards · quick recall practice
More Process Questions
View all →You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. During month 6, you conduct an earned value analysis and discover that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks you to forecast the final project cost and determine what actions are needed. Using the current performance trends, what is the most appropriate estimate at completion (EAC) if you believe current variances are atypical and future work will be performed at the planned rate?
You are leading a software development project using a predictive approach. The project sponsor has approved the project charter, and you are now ready to begin detailed planning. Your next step is to gather requirements from stakeholders to understand what the software must accomplish. Which process group are you currently working in?
You are managing a bridge construction project and have just completed developing the Work Breakdown Structure (WBS) with your team. Each work package has been defined and assigned a unique identifier. A team member asks what the lowest level of the WBS represents. How should you respond?
