PMP Practice Question: People — Hybrid, Medium
You are leading a product development project using a hybrid approach with quarterly planning cycles and two-week Scrum sprints. A senior developer who is critical to delivery has submitted their resignation with a four-week notice period. This developer is the only team member with expertise in the legacy integration system. The project is currently 60% complete with a fixed deadline in five months. What should be your priority action?
Study this topic
- 📖Risk Management PMP Exam: Complete Strategic Guide
Master risk management for the PMP exam with strategic insights on identification, assessment, and response planning aligned with PMBOK 8 principles.
- 📖Will AI Replace Project Managers? The Honest Answer
Explore the realistic impact of AI on project management careers, what the 2026 PMP exam teaches about AI integration, and how to future-proof your PM skills.
- 🗂️Flashcards: Leadership, Team & Stakeholder Models
15 cards · quick recall practice
More People Questions
View all →You are managing a construction project using a predictive approach. The project is in the execution phase, and you have a baseline schedule with clearly defined milestones. One of your key team members, who is responsible for electrical installations, requests three weeks of leave for personal reasons during a critical phase of the project. This team member has specialized expertise that is difficult to replace. The leave would occur just before a major milestone delivery. What is the BEST course of action?
You are leading a manufacturing facility construction project following a predictive lifecycle. The project team consists of 15 members, including contractors and internal staff. After three months of work, you receive feedback from several team members that the weekly status meetings are too long and not productive. Team members feel they spend too much time listening to updates irrelevant to their work. The meetings currently last 90 minutes and cover all work packages. What is the best approach to address this concern?
You are leading a manufacturing implementation project using a predictive lifecycle. The project team consists of members from three different departments who have not worked together before. After one month of execution, you observe that team members primarily communicate within their departmental groups, and cross-functional collaboration is minimal. Work hand-offs between departments are experiencing delays and quality issues. The project charter emphasizes the importance of integrated teamwork for project success. What should you do to improve this situation?