PMP Practice Question: ProcessAgile, Medium

Your agile team has been delivering consistent increments every two weeks for six months. A new senior stakeholder joins the project and requests a detailed Gantt chart showing all remaining features with specific completion dates for the next six months. The product owner is concerned this stakeholder may not understand the agile approach. The stakeholder has significant influence over project funding. How should you respond to this request?