PMP Practice Question: Process — Hybrid, Easy

A project team is using a hybrid approach where requirements are gathered upfront but development is executed in two-week sprints. The product owner has just requested a new feature that was not in the original project scope. The team has completed three sprints and has five more planned. What should the project manager do first?