You are managing a manufacturing project to deliver 500 custom components over 10 months. After 4 months, you have delivered 180 components. The project budget is $500,000, and you have spent $195,000 so far. According to the baseline schedule, you should have delivered 200 components by now. Senior management wants to know if the project will meet its deadline. What is the Schedule Performance Index (SPI) and what does it indicate about schedule performance?