PMP Practice Question: Process — Agile, Medium

Your agile team has completed three sprints of a mobile application development project. During the retrospective, the team identifies that their velocity has been declining from 45 story points in Sprint 1 to 38 in Sprint 2, and 32 in Sprint 3. Team members mention they are spending significant time waiting for answers from the product owner, who is often unavailable due to other commitments. The product owner attends sprint planning and reviews but is rarely available during the sprint. What should the project manager do first to address this situation?