PMP Practice Question: People — Hybrid, Medium
During a retrospective for your hybrid project, several team members express concern that the daily standups aren't effective because the predictive-focused team members provide lengthy updates about their tasks while the agile-focused members give brief updates. This is causing the meetings to regularly exceed 30 minutes, and some team members have started skipping them. The team is struggling to maintain alignment across both work streams. As the project manager, what should you do to improve team engagement?
Study this topic
- 📖Motivating Teams Through Servant Leadership Principles
Discover how servant leadership transforms project team motivation by putting people first, removing obstacles, and creating environments where teams thrive and deliver exceptional value.
- 📖Coaching and Mentoring in Agile Teams: A PMP Perspective
Learn how servant leadership, coaching, and mentoring drive agile team performance. Essential knowledge for PMP candidates preparing for the 2026 exam's expanded agile focus.
- 🗂️Flashcards: Leadership, Team & Stakeholder Models
15 cards · quick recall practice
More People Questions
View all →You are managing a construction project using a predictive approach. The project is in the execution phase, and you have a baseline schedule with clearly defined milestones. One of your key team members, who is responsible for electrical installations, requests three weeks of leave for personal reasons during a critical phase of the project. This team member has specialized expertise that is difficult to replace. The leave would occur just before a major milestone delivery. What is the BEST course of action?
You are leading a manufacturing facility construction project following a predictive lifecycle. The project team consists of 15 members, including contractors and internal staff. After three months of work, you receive feedback from several team members that the weekly status meetings are too long and not productive. Team members feel they spend too much time listening to updates irrelevant to their work. The meetings currently last 90 minutes and cover all work packages. What is the best approach to address this concern?
You are leading a manufacturing implementation project using a predictive lifecycle. The project team consists of members from three different departments who have not worked together before. After one month of execution, you observe that team members primarily communicate within their departmental groups, and cross-functional collaboration is minimal. Work hand-offs between departments are experiencing delays and quality issues. The project charter emphasizes the importance of integrated teamwork for project success. What should you do to improve this situation?