ProcessAgileMediumECO: Process Task 5.1

During a sprint review, stakeholders see the completed user stories but express disappointment that the features don't match their expectations. The team followed the acceptance criteria precisely, and all stories meet the Definition of Done. The product owner approved the stories during backlog refinement two weeks ago. Stakeholders now request significant changes that would require reworking most of the sprint's output. What is the most appropriate next step?