You are managing a construction and technology project using a hybrid approach. Physical construction follows a critical path method schedule, while the building automation system development uses Kanban. The construction team has identified that they will complete the electrical rough-in two weeks ahead of schedule, which would allow the automation team to begin installation earlier than planned. However, the automation team's Kanban board shows they are currently focused on software configuration and have not yet started the installation work packages. What should you do?