PMP Practice Question: Process — Agile, Medium

Your Kanban team has been tracking their flow metrics, and you notice the average cycle time has increased from 4 days to 7 days over the past month. The team's WIP limits haven't changed, and the work item types are consistent with previous months. During a team discussion, you discover that items are spending significantly more time in the 'Code Review' column, often waiting 2-3 days before being reviewed. Team members mention they're focused on completing their own work before reviewing others' contributions. What should the team do to address this issue?