Your product has been using two-week sprints successfully for eight months. Recently, market dynamics have accelerated, with competitors releasing features weekly. Your executive sponsor wants the team to switch to one-week sprints to 'move faster and be more agile.' The team is concerned this will increase ceremony overhead and reduce their actual development time. When you analyze the data, you find the team averages 1.5 days of ceremonies per sprint and typically doesn't have testable increments until day 9-10 of the current sprint. What recommendation best addresses the sponsor's concern while maintaining team effectiveness?