PMP Guide — Empowering Project Managers
ProcessAgileHardECO: Process Task 3.10

Your product has been using two-week sprints successfully for eight months. Recently, market dynamics have accelerated, with competitors releasing features weekly. Your executive sponsor wants the team to switch to one-week sprints to 'move faster and be more agile.' The team is concerned this will increase ceremony overhead and reduce their actual development time. When you analyze the data, you find the team averages 1.5 days of ceremonies per sprint and typically doesn't have testable increments until day 9-10 of the current sprint. What recommendation best addresses the sponsor's concern while maintaining team effectiveness?

← All questions
📖

Study this topic

WBS Work Breakdown Structure: Proven Best Practices

Master the essential techniques for creating effective Work Breakdown Structures that drive project success and align wi

More Process Questions

View all →
1
MediumPredictive

Your manufacturing equipment upgrade project is in the executing phase. A key vendor has submitted deliverables for the third milestone, but during the inspection process, your quality assurance team identifies that 15% of the components do not meet the specifications outlined in the procurement contract. The vendor claims the specifications were ambiguous and requests additional payment to remake the components. This is causing a potential two-week delay. What is the BEST course of action?

2
MediumPredictive

You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. During month 6, you conduct an earned value analysis and discover that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks you to forecast the final project cost and determine what actions are needed. Using the current performance trends, what is the most appropriate estimate at completion (EAC) if you believe current variances are atypical and future work will be performed at the planned rate?

3
MediumHybrid

You are leading a regulatory compliance project using a hybrid approach where legal requirements are managed predictively with sequential gate approvals, while technical implementation uses iterative sprints. After three sprints, the compliance team reviews the working software and identifies that two implemented features may not fully satisfy regulatory requirements. The development team argues that requirements were ambiguous and their interpretation was reasonable. The next compliance gate is in two weeks. What is the best course of action?

PMP Practice Question — Process · Hard | PMP Guide