ProcessHybridMediumECO: Process Task 2.4

Your hybrid project uses a predictive approach for hardware procurement and an adaptive approach for software development. During a sprint review, stakeholders request a significant feature enhancement that would require additional hardware components with a 10-week lead time. The current sprint has three weeks remaining, and four more sprints are planned. The product owner wants to add this feature to the product backlog immediately. What is the most appropriate action?