You are facilitating sprint planning for a three-week sprint. The product owner presents the prioritized backlog, and the team begins selecting user stories. After selecting six stories totaling 24 story points, three team members mention they have committed to attending a mandatory company training program that will take them away for three full days during the sprint. What should the team do?