You are managing a large infrastructure project with a 24-month timeline and a fixed budget of $15 million. At the end of month 12, you conduct an earned value analysis and find: PV = $7.5M, EV = $6.8M, AC = $7.9M. The sponsor is concerned about cost overruns and asks whether the project can be completed within the original budget. Your team estimates that current performance trends will continue. What is the most accurate estimate at completion (EAC) you should report to the sponsor?