You are facilitating sprint planning for a new feature that involves complex data migration. The development team estimates the work at 34 story points, but the sprint capacity is only 28 story points based on historical velocity. One developer suggests reducing quality checks to fit everything into the sprint, while another proposes splitting the migration into smaller, independently deliverable chunks. The product owner is concerned about delaying the feature launch. How should you proceed with sprint planning?