PMP Practice Question: PeopleHybrid, Easy

You are managing a hybrid project where the development team uses Scrum for product features while the compliance team works using a predictive approach for regulatory documentation. During a recent sprint review, several compliance team members expressed frustration that they were not informed about feature changes until after development was complete, causing rework in their documentation. The development team claims they are following their sprint process correctly. What should you do first to address this issue?

← All questions
📖

Study this topic

Breaking Into Project Management: PMP Certification for Career Changers

Career changers face unique challenges pursuing PMP certification. Learn how to meet eligibility requirements, build pro

More People Questions

View all →
1
MediumAgile

During sprint planning, your development team commits to 45 story points based on historical velocity. However, your product owner insists they must complete 60 story points this sprint because of a commitment made to a key stakeholder. The product owner argues that the team 'just needs to work harder' and threatens to escalate to senior management if the team doesn't comply. The team looks to you, the Scrum Master, for guidance. How should you respond?

2
MediumAgile

Your agile team has a new member, Sarah, who joined two weeks ago. Sarah has strong technical skills but comes from a traditional waterfall background. During the current sprint, you notice Sarah working in isolation, not updating the task board, and not asking for help despite her story being blocked. In the standup, she reports 'everything is fine' even though you can see she's struggling. Other team members have offered help, but she politely declines. What is the most effective way to help Sarah adapt to the agile team environment?

3
MediumAgile

Your agile team has been consistently meeting sprint commitments, but during a recent retrospective, team members admitted they have been padding estimates significantly to ensure they never miss a commitment. The team's capacity allows them to complete stories early, but they wait until late in the sprint to pull in additional work to avoid looking like they overcommitted. The product owner is frustrated because the team could be delivering more value. What should you do to address this behavior?