ProcessAgileMediumECO: Process Task 3.3

PMP Practice Question: Process — Agile, Medium

During sprint planning, your development team is struggling to break down a large user story estimated at 21 story points. The Product Owner insists this story must be completed in the upcoming two-week sprint because it's critical for an upcoming trade show demonstration. The team expresses concern that they typically complete 25-30 story points per sprint, but this single story would consume most of their capacity and carries significant technical risk. The story cannot be demonstrated partially. What is the best approach?