PMP Guide — Empowering Project Managers
ProcessHybridHardECO: Process Task 1.14

PMP Practice Question: Process — Hybrid, Hard

Your hybrid project combines predictive hardware development with agile firmware iterations. The hardware team has completed their design phase and moved into manufacturing (month 8 of 14), while the firmware team is in sprint 12 of 20. During sprint 12, the firmware team discovers that achieving optimal performance requires a minor hardware modification that would cost $45K and delay manufacturing by 3 weeks. Without this change, the product will meet minimum specifications but perform 25% slower than competitors. The product owner wants to make the change, but the hardware lead argues the decision should follow the formal change control process with steering committee approval, which meets monthly. What should you do?

← All questions

Study this topic