PMP Guide — Empowering Project Managers
ProcessPredictiveMediumECO: Process Task 2.2

PMP Practice Question: Process — Predictive, Medium

You are managing a telecommunications infrastructure project using a predictive methodology. The project is 60% complete when you conduct an earned value analysis. The results show: PV = $800,000, EV = $720,000, AC = $780,000, BAC = $1,200,000. Based on these metrics, the project team is concerned about performance. The sponsor asks you to forecast the total cost at completion and explain the project's current performance status. What is the most accurate assessment?

← All questions

Study this topic

PMP Practice Question — Process · Medium | PMP Guide