PMP Practice Question: Process — Predictive, Medium
You are managing a telecommunications infrastructure project using a predictive methodology. The project is 60% complete when you conduct an earned value analysis. The results show: PV = $800,000, EV = $720,000, AC = $780,000, BAC = $1,200,000. Based on these metrics, the project team is concerned about performance. The sponsor asks you to forecast the total cost at completion and explain the project's current performance status. What is the most accurate assessment?
Study this topic
- 📖Earned Value Management: Your PMP Exam Formula Survival Guide
Master EVM formulas, interpret performance metrics, and tackle calculation questions with confidence. Essential Process domain knowledge for PMP success.
- 📖Earned Value Management: Complete PMP Exam Study Guide
Master EVM formulas, interpretation, and application for the PMP exam. Learn how earned value management integrates with agile, hybrid, and predictive approaches in the 2026 ECO.
- 🗂️Flashcards: Earned Value Management (EVM) Formulas
16 cards · quick recall practice
More Process Questions
View all →You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. During month 6, you conduct an earned value analysis and discover that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks you to forecast the final project cost and determine what actions are needed. Using the current performance trends, what is the most appropriate estimate at completion (EAC) if you believe current variances are atypical and future work will be performed at the planned rate?
You are leading a software development project using a predictive approach. The project sponsor has approved the project charter, and you are now ready to begin detailed planning. Your next step is to gather requirements from stakeholders to understand what the software must accomplish. Which process group are you currently working in?
You are managing a bridge construction project and have just completed developing the Work Breakdown Structure (WBS) with your team. Each work package has been defined and assigned a unique identifier. A team member asks what the lowest level of the WBS represents. How should you respond?
