Your agile team is developing a customer relationship management (CRM) system. The product owner has created a prioritized product backlog with 45 user stories. Several stakeholders are asking when specific features will be delivered. The team has completed two sprints, delivering 12 and 11 story points respectively. What is the best way to provide stakeholders with delivery expectations?