ProcessHybridMediumECO: Process Task 1.5

You are leading a hybrid project where the design phase follows a predictive approach with fixed milestones, while implementation uses iterative delivery. During the third implementation iteration, the team discovers that a design assumption documented in the approved design specification is technically infeasible. Implementing the original design would require significant rework. The design phase gate was formally closed two months ago. How should you proceed?