PMP Practice Question: Process — Hybrid, Medium
You are leading a hybrid project where the design phase follows a predictive approach with fixed milestones, while implementation uses iterative delivery. During the third implementation iteration, the team discovers that a design assumption documented in the approved design specification is technically infeasible. Implementing the original design would require significant rework. The design phase gate was formally closed two months ago. How should you proceed?
Study this topic
- 📖PMI-PMOCP: The New PMO Certification Every Leader Should Know
PMI's PMO-CP certification validates enterprise-level PMO expertise. Learn what it covers, who should pursue it, and how it differs from PMP.
- 📖Governance Frameworks and PMO for the 2026 PMP Exam
Master governance frameworks and PMO structures for the 2026 PMP exam. Learn how organizational governance connects to the expanded Business Environment domain.
- 🗂️Flashcards: Agile, Scrum & Hybrid Concepts
15 cards · quick recall practice
More Process Questions
View all →You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. During month 6, you conduct an earned value analysis and discover that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks you to forecast the final project cost and determine what actions are needed. Using the current performance trends, what is the most appropriate estimate at completion (EAC) if you believe current variances are atypical and future work will be performed at the planned rate?
You are leading a software development project using a predictive approach. The project sponsor has approved the project charter, and you are now ready to begin detailed planning. Your next step is to gather requirements from stakeholders to understand what the software must accomplish. Which process group are you currently working in?
You are managing a bridge construction project and have just completed developing the Work Breakdown Structure (WBS) with your team. Each work package has been defined and assigned a unique identifier. A team member asks what the lowest level of the WBS represents. How should you respond?
