PMP Practice Question: Process — Agile, Hard

Your distributed agile team spans three time zones with only a two-hour daily overlap. Sprint planning consistently runs over time, with the India-based developers joining at 6 AM their time and the US-based product owner available only until 11 AM EST. Retrospectives reveal that 40% of stories require significant rework because developers interpreted requirements differently than intended. The team has tried detailed acceptance criteria, but misunderstandings persist. Team velocity is 30% below similar co-located teams. What structural change would most effectively address this challenge?