PMP Practice Question: Process — Predictive, Medium

Your construction project is halfway through execution when you discover that actual costs are significantly higher than planned. The Cost Performance Index (CPI) is 0.78 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks for your assessment of the situation and whether the project can be completed within the approved budget. You have $2 million remaining in the budget and estimate $3.2 million of work left to complete. What is the most appropriate course of action?