ProcessHybridHardECO: Process Task 3.16

You are leading a hybrid project implementing a new customer relationship management (CRM) system. The infrastructure and data migration components are being executed using predictive approaches with detailed schedules, while the user interface customization is being developed iteratively with two-week sprints. During Sprint 3, the development team discovers that database schema changes required for a new UI feature will impact the data migration timeline, which is currently on the critical path. The infrastructure team needs three weeks to implement the schema changes, but this will delay the overall project completion by two weeks. What should you do first?