ProcessAgileHardECO: Process Task 3.16

Your agile team has been delivering features every two weeks for six months. During the latest sprint review, a key stakeholder expresses frustration that the product increment doesn't align with their vision, despite approving stories throughout development. The product owner admits they've been accepting stories based on technical completion rather than business value validation. Technical debt has accumulated, and the team's velocity has dropped 30% over the last three sprints. What should you do first to address this systemic issue?