PMP Practice Question: People — Predictive, Hard

You are managing a large construction project that has entered the execution phase. During a routine performance review, you discover that one of your site supervisors has been consistently inflating progress reports for the past three weeks, showing 85% completion when actual completion is closer to 65%. This supervisor is well-liked by the team, has 15 years of experience, and this is the first time you've encountered integrity issues with this individual. The misinformation has affected your earned value calculations and led you to reassign resources that were actually still needed. The project is visible to executive leadership, and you have a steering committee meeting in two days. What is the most appropriate course of action?

← All questions

Study this topic

More People Questions

View all →
1
MediumPredictive

You are managing a construction project using a predictive approach. The project is in the execution phase, and you have a baseline schedule with clearly defined milestones. One of your key team members, who is responsible for electrical installations, requests three weeks of leave for personal reasons during a critical phase of the project. This team member has specialized expertise that is difficult to replace. The leave would occur just before a major milestone delivery. What is the BEST course of action?

→
2
MediumPredictive

You are leading a manufacturing facility construction project following a predictive lifecycle. The project team consists of 15 members, including contractors and internal staff. After three months of work, you receive feedback from several team members that the weekly status meetings are too long and not productive. Team members feel they spend too much time listening to updates irrelevant to their work. The meetings currently last 90 minutes and cover all work packages. What is the best approach to address this concern?

→
3
MediumPredictive

You are leading a manufacturing implementation project using a predictive lifecycle. The project team consists of members from three different departments who have not worked together before. After one month of execution, you observe that team members primarily communicate within their departmental groups, and cross-functional collaboration is minimal. Work hand-offs between departments are experiencing delays and quality issues. The project charter emphasizes the importance of integrated teamwork for project success. What should you do to improve this situation?

→
PMP Practice Question — People · Hard | PMP Guide