During sprint planning, your development team commits to 45 story points based on their historical velocity. However, the product owner is frustrated because stakeholders are pressuring for more features to be delivered faster. The product owner asks you to challenge the team to commit to 60 story points this sprint, arguing that the team needs to 'push themselves' and that previous sprints didn't have enough urgency. The team appears uncomfortable with this request. How should you respond?