PMP Practice Question: Process — Agile, Medium
Your development team has been consistently achieving their sprint goals for the past four sprints with a stable velocity of 30 story points. In sprint planning for the next iteration, the team commits to 30 points of work. However, by mid-sprint during the daily standup, it becomes clear that three critical stories are blocked due to an unexpected production outage requiring immediate team attention. The team estimates they can only complete 18 points this sprint. What should the scrum master do?
Study this topic
- 📖Agile Sprint Planning Techniques for the 2026 PMP Exam
Master sprint planning techniques essential for the 2026 PMP exam. Learn how to apply timeboxing, capacity planning, and story estimation in hybrid environments.
- 📖Risk Management PMP Exam: Complete Strategic Guide
Master risk management for the PMP exam with strategic insights on identification, assessment, and response planning aligned with PMBOK 8 principles.
- 🗂️Flashcards: Agile, Scrum & Hybrid Concepts
15 cards · quick recall practice
More Process Questions
View all →You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. During month 6, you conduct an earned value analysis and discover that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks you to forecast the final project cost and determine what actions are needed. Using the current performance trends, what is the most appropriate estimate at completion (EAC) if you believe current variances are atypical and future work will be performed at the planned rate?
You are leading a software development project using a predictive approach. The project sponsor has approved the project charter, and you are now ready to begin detailed planning. Your next step is to gather requirements from stakeholders to understand what the software must accomplish. Which process group are you currently working in?
You are managing a bridge construction project and have just completed developing the Work Breakdown Structure (WBS) with your team. Each work package has been defined and assigned a unique identifier. A team member asks what the lowest level of the WBS represents. How should you respond?