ProcessAgileMediumECO: Process Task 4.4

Your development team has been consistently achieving their sprint goals for the past four sprints with a stable velocity of 30 story points. In sprint planning for the next iteration, the team commits to 30 points of work. However, by mid-sprint during the daily standup, it becomes clear that three critical stories are blocked due to an unexpected production outage requiring immediate team attention. The team estimates they can only complete 18 points this sprint. What should the scrum master do?