PeoplePredictiveHardECO: People Task 1.9

You are managing a large government infrastructure project with a baseline budget of $45 million and a 24-month timeline. At month 16, a critical team member who holds specialized knowledge about legacy system integration submits their resignation, citing personal reasons. This team member has been instrumental in interfacing with three key stakeholders and possesses undocumented institutional knowledge. The project is currently on schedule but slightly over budget (CPI 0.92). Your sponsor is concerned about the impact on the upcoming integration phase scheduled to begin in three weeks. What should be your FIRST action to address this situation?