Your hybrid project includes both traditional procurement activities managed through a stage-gate process and agile development work managed through Scrum. A critical vendor deliverable scheduled for the end of Stage 2 has been delayed by three weeks. The development team has planned the next two sprints based on receiving this deliverable at the originally scheduled time. The vendor cannot accelerate delivery, and the delay will impact six planned user stories. What should you do?