ProcessPredictiveEasyECO: Process Task 1.2 - Manage project compliance

PMP Practice Question: Process — Predictive, Easy

Your project to develop a new financial reporting system has a budget of $500,000 and is scheduled to take 10 months. You are currently at the end of month 4. According to your tracking, you have spent $220,000 and completed work that was budgeted at $180,000. What is the cost performance of your project at this point?