You are managing a marketing campaign project using a hybrid approach. The creative content development uses Scrum sprints, while media buying and placement follow a predictive schedule tied to specific launch dates. During sprint review, stakeholders are extremely pleased with the creative work completed and want to launch two weeks earlier than planned. However, the media buying contracts are already finalized for the original dates, and changing them would incur significant penalties. How should you respond to this request?