PMP Practice Question: Process — Agile, Hard
Your agile team has completed three sprints of a mobile application project. The product owner consistently adds new acceptance criteria during sprint reviews, claiming these represent newly discovered customer needs. The team's velocity has dropped from 45 to 28 story points, and team members are frustrated with rework. The product owner insists all changes are critical for market competitiveness. Sprint planning for the next iteration is scheduled for tomorrow. What should the Scrum Master do first to address this situation?
Study this topic
- 📖Psychological Safety in Project Teams: A PMP Essential
Psychological safety drives team performance and innovation. Learn how to create trust, encourage risk-taking, and build high-performing project teams aligned with PMBOK 8 principles.
- 📖Financial Management for Project Managers: PMP 2026 Guide
Master financial management for the 2026 PMP exam. Learn budgeting, earned value, and business case analysis aligned with the expanded Business Environment domain.
- 🗂️Flashcards: Leadership, Team & Stakeholder Models
15 cards · quick recall practice
More Process Questions
View all →You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. During month 6, you conduct an earned value analysis and discover that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks you to forecast the final project cost and determine what actions are needed. Using the current performance trends, what is the most appropriate estimate at completion (EAC) if you believe current variances are atypical and future work will be performed at the planned rate?
You are leading a software development project using a predictive approach. The project sponsor has approved the project charter, and you are now ready to begin detailed planning. Your next step is to gather requirements from stakeholders to understand what the software must accomplish. Which process group are you currently working in?
You are managing a bridge construction project and have just completed developing the Work Breakdown Structure (WBS) with your team. Each work package has been defined and assigned a unique identifier. A team member asks what the lowest level of the WBS represents. How should you respond?