Your agile team has completed three sprints of a mobile application project. The product owner consistently adds new acceptance criteria during sprint reviews, claiming these represent newly discovered customer needs. The team's velocity has dropped from 45 to 28 story points, and team members are frustrated with rework. The product owner insists all changes are critical for market competitiveness. Sprint planning for the next iteration is scheduled for tomorrow. What should the Scrum Master do first to address this situation?